February 12th we were at the Centre Culturel in Erpeldange, where we were able to introduce ourselves as the Energiekooperativ Kanton Remich and also present our goals. We also presented and explained our completed and future projects.
Since August 16, 2023, the Boulodrome has produced a total of 35.52 MWh of electricity. The installation at the School of Mondorf, which has been running since November 11, 2024, has produced a total of 5.02 MWh of electricity. (Situation of February 17, 2025)
The project concerning the Centre Culturel, where this information evening took place, was also presented. The installation in Erpeldange is expected to be a 20.80 kWp system that will produce electricity for 8 single-family houses. The investment is estimated at around 23,000€.




After the presentation, there was an interesting Q&A session, and afterward, the municipality invited everyone for a drink.
We would like to thank everyone who found their way to Erpeldange at the Centre Culturel on that day.
Information Evening at Erpeldange
February 12th we were at the Centre Culturel in Erpeldange, where we were able to introduce ourselves as the Energiekooperativ Kanton Remich and also present our goals. We also presented and explained our completed and future projects.
Since August 16, 2023, the Boulodrome has produced a total of 35.52 MWh of electricity. The installation at the School of Mondorf, which has been running since November 11, 2024, has produced a total of 5.02 MWh of electricity. (Situation of February 17, 2025)
The project concerning the Centre Culturel, where this information evening took place, was also presented. The installation in Erpeldange is expected to be a 20.80 kWp system that will produce electricity for 8 single-family houses. The investment is estimated at around 23,000€.




After the presentation, there was an interesting Q&A session, and afterward, the municipality invited everyone for a drink.
We would like to thank everyone who found their way to Erpeldange at the Centre Culturel on that day.
Commissioning of the second PV system
On November 12, 2024, the second PV system of EKR was inaugurated together with the electric stations from Petro-Center. This system could only be realized with the support of its members. Minister Lex Delles did not miss the opportunity to be present at the double inauguration. We are extremely pleased with his support, as well as that of Mayor Steve Reckel and the team from the municipality of Mondorf.




With a capacity of around 68 kWp, this system at the school in Mondorf is more than twice as large as the one at the Boulodrome. The timing, as always, was excellent, as this system was connected to the grid just one day before the inauguration, on November 11, 2024.
General Assembly.
On June 26, 2024, we held our first General Assembly. It took place in the Citizen and Culture House in Mondorf.
We would like to thank all of you for making the effort to attend our first GA.
After addressing the usual items discussed at a GA, we also presented the production from the Boulodrome. From August 16, 2023, to June 31, 2024, 21.51 MWh of electricity was produced.
Furthermore, a new project that will be realized this year, along with other projects in the pipeline, was presented.




In conclusion, another informational meeting was announced, which will take place on July 10 in Remich.
After the interesting and active General Assembly, many engaging conversations were started and continued over a drink.